Construction

May

In late May the plans were submitted to engineering. The demo continued and some repair under the two rooms that were not disturbed
Supports were built underneath the floor to hold up the floor as perimeter beams were replaced as all were damaged beyond repair. Some floor joists were replaced as well. This took -A while
More evidence of termite and water damage
JUNE

Some reconstruction of floors that did not require engineering
June 26. Engineering is done. Framing to begin next week
Lumber dropped!
July 7th. Floor joists are done!
Decking and walls and ceiling July week 3
Stairs to attic!